Denver, Co
CENTRAL I-70
Concrete Cutting / Transportation

Type of project?
-
Central I-70 project of knocking down the viaduct
-
5-year project
-
Precision concrete cutting
-
Full service: Concrete cutting, curb sawing
What is the purpose of the project?
-
Reconstruct a 10-mile stretch of the I-70
-
Widen lanes to include an express lane on each side
-
Remove the 55-year-old viaduct
-
Lower a portion of the interstate and construct a 4-acre park above
-
Noise reduction to accommodate increased population traffic flow
Estimated completion date?
-
Start: September 2018
-
Estimated Completion: 4-5 years – A-Core has been contracted to be working for the entire duration of the project
Challenges of the project?
-
A lot of curb sawing had to be done
-
A-Core was the only company in the area that had the ability and expertise to do that










